VINELAND MIDDLE SCHOOL BOND PROJECTS
UPGRADE ROOF
Current Status: Design Development
Scheduled to begin: 4/2022
The existing roof has reached the end of its expected life and will be replaced with a new, high-quality roof system that has a 22-30 year life-span, is energy-efficient and environmentally friendly.
REPLACE ROOFTOP UNITS
Current Status: Design Development
Scheduled to begin: 6/2022
The existing heating/cooling units are at the end of their expected life and inefficient. Replacing these with new, high-efficiency rooftop heating/cooling units will produce substantial long-term energy savings and improved building comfort. Old control hardware will be replaced and integrated into the District’s control system to optimize the performance of the new units.
REDESIGN PARENT & BUS LOOPS, FIX DRAINAGE
Current Status: Design Development
Scheduled to begin: 6/2022
Traffic flow is a major safety issue. Reconfiguration of the parent loop, bus loop, and parking lot will provide separation of these activities and improve traffic patterns, especially during high volume times. The main parking will be improved to address the drainage issues and to keep water from flowing toward the school entrance. The dirt lot next to the main parking lot will be paved to provide additional parking.
FIX DRAINAGE NORTHEAST OF TRACK
Current Status: Design Development
Scheduled to begin: 6/2022
In order to resolve the drainage issues on the northeast end of the track, the dirt area above the track will be repurposed as a small retention basin, to be used as needed.
REPLACE BLEACHERS
Current Status: IN PROGRESS
The outdated and unserviceable gymnasium bleachers will be replaced with new bleachers that can seat 350+ people.
REPLACE CEILINGS
Current Status: Design Development
Scheduled to begin: 6/2022
Replacing old and damaged drop ceiling tiles throughout the building will significantly improve the aesthetics in the building.