VINELAND ELEMENTARY SCHOOL
Vineland Projects Begin
Summer 2021
VINELAND ELEMENTARY SCHOOL BOND PROJECTS
UPGRADE ROOF
Current Status: COMPLETE
A new roof will be installed on the original portion of the school, eliminating problematic leaks throughout the facility. The new, high-quality roof system will have a 22-30 year life-span, is energy-efficient and environmentally friendly. The interior damage caused by leaks will be repaired and damaged soffits will be replaced.
REPLACE ROOFTOP UNITS
Current Status: Complete
The existing heating/cooling units are at the end of their expected life and inefficient. Replacing these with new, high-efficiency rooftop heating/cooling units will produce substantial long-term energy savings and improved building comfort.
NEW CONTROLS SYSTEM
Current Status: In Progress
All existing control hardware will be replaced, and the new equipment will be integrated into the District’s control system to optimize the performance of the new heating/cooling systems and provide additional energy efficiency.
RENOVATE LIBRARY AND COMPUTER LAB
Current Status: Design Development
Scheduled to begin: 6/2022
The library and computer lab will be reconfigured and modernized to provide better learning and workspaces for students.
ADD OUTDOOR CLASS SPACE
Current Status: Design Development
A new outdoor classroom will be created with a concrete pad and an open-side pole barn with seating to provide shade and protection from the elements. ADA accessibility will be provided by a ramp from the main building to the outdoor space. Handrails will be added to the stairs for additional safety.
ACCESS CONTROL FOR EAST DOORS
Current Status: IN PROGRESS
Key card access will be added to three high-use exterior doors. Key card access provides easier access for staff and provides additional security.
BASEMENT ACCESS RENOVATION
Current Status: In Progress
Scheduled to begin: 2/2022
The existing interior basement entrance fence will be demolished and replaced with a fire-rated wall and fire door.